NotablePrimary completion pushed from Oct 30, 2026 to Jun 25, 2027
Study completion pushed from Oct 31, 2026 to Jun 25, 2027
Study sites revised (9)
Eligibility criteria expanded, about 5 words
NotablePrimary completion date: Mar 30, 2026 to Oct 30, 2026
Study completion date: Mar 31, 2026 to Oct 31, 2026
Site details revised at 2 of 9 sites
v32
MinorPrimary completion date: Dec 31, 2025 to Mar 30, 2026
Study completion date: Dec 31, 2025 to Mar 31, 2026
Site details revised at 1 of 9 sites
v31
MinorPrimary and study completion dates: Sep 30, 2025 to Dec 31, 2025v30
MinorRe-verified, no change to tracked fieldsv29
Show 27 earlier versionsHide 27 earlier versions
MinorPrimary completion date: May 29, 2025 to Sep 30, 2025
Study completion date: May 30, 2025 to Sep 30, 2025
Site details revised at 1 of 9 sites
v28
MinorEnrollment target: 99 to 98
Primary completion date: Feb 28, 2025 to May 29, 2025
Study completion date: Feb 28, 2025 to May 30, 2025
Site details revised at 1 of 9 sites
v27
MinorEnrollment target: 98 to 99
Primary completion date: Dec 20, 2024 to Feb 28, 2025
v26
MinorPrimary completion date: May 16, 2025 to Dec 20, 2024
Study completion date: May 16, 2025 to Feb 28, 2025
Study sites revised (9)
v25
MinorPrimary and study completion dates: Dec 20, 2024 to May 16, 2025
Site details revised at 1 of 9 sites
v24
MinorPrimary and study completion dates: Sep 12, 2024 to Dec 20, 2024
Study sites revised (9)
v23
MinorPrimary and study completion dates: May 16, 2025 to Sep 12, 2024v22
NotablePrimary and study completion dates: Apr 29, 2024 to May 16, 2025v21
MinorEnrollment target: 99 to 98v20
MinorPrimary and study completion dates: Mar 29, 2024 to Apr 29, 2024v19
NotablePrimary and study completion dates: May 16, 2025 to Mar 29, 2024v18
NotablePrimary and study completion dates: Mar 29, 2024 to May 16, 2025v17
NotablePrimary and study completion dates: May 16, 2025 to Mar 29, 2024v16
MinorTrial status: Recruiting to Active, Not Recruiting
Enrollment target: estimated 380 to confirmed 99
Site details revised at 9 of 9 sites
v15
NotablePrimary and study completion dates: Apr 15, 2024 to May 16, 2025
Site contacts updated at 3 of 9 sites
v14
NotablePrimary and study completion dates: Apr 14, 2023 to Apr 15, 2024
Site contacts updated at 2 of 9 sites
v13
MinorEligibility criteria expanded, about 17 words
Secondary endpoints: 9 to 8
Site contacts updated at 1 of 9 sites
v12
MinorRe-verified, no change to tracked fieldsv11
MinorStudy sites: 7 to 9v10
MinorStudy sites: 6 to 7v9
MinorEnrollment target: 320 to 380v8
MinorRe-verified, no change to tracked fieldsv7
MinorStudy sites: 5 to 6
Primary and study completion dates: Nov 28, 2022 to Apr 14, 2023
v6
MinorStudy sites: 3 to 5v5
MinorRe-verified, no change to tracked fieldsv4
NotableTrial status: Not Yet Recruiting to Recruiting
Study sites: 0 to 3
Start date changed from estimate of Apr 18, 2019 to May 7, 2019
v3
MinorRe-verified, no change to tracked fieldsv2
MinorStudy First Submitted
Notable: the trial’s plan changed such as a big move in its timeline or size, a new primary endpoint, sponsor or phase, or recruiting opened or resumed.
Minor: routine progress and housekeeping, such as sites added or enrollment closed.
This is a phase I/Ib, open label study. The escalation portion will characterize the safety and tolerability of DKY709 and DKY709 in combination with PDR001 in subjects with NSCLC or melanoma who have received prior anti-PD-1/PD-L1 therapy, or subjects with NPC. After the determination of the MTD/RD for a particular treatment arm, dose expansion will further assess safety, tolerability, PK/PD, and anti-tumor activity of each regimen at the MTD/RD.